|
|
Town
Hall: Fallacies and Faults
By Dan Sapir
(September 18, 2003)
It’s terrific that the seat of government is
moving into the new Town Hall by month’s end. The replacement of the old
Green Facility has been a long time in the making and was the right
decision. Many memories will be left behind and the names of those who
served there would fill a novel. From the attic, which few had ever seen,
perhaps mercifully so, to the lower level that once housed the police
department, and prisoners, to the main level selectmen chambers, the scene
of many political wars, the building served us well. The community sought to
fund a new structure and to do so on land we already owned and at a site
that forms the approximate center of town. The project, for a time was under
budget, and the Building Committee did a reasonably good job. As always
however, we should learn from our mistakes. While we continue to read puff
pieces about the upcoming heralded event, let’s take a look at some of the
matters you have never heard of.
Handicapped Access:
June Ball-inger and Christina Willis must be wincing from above. It was
discovered that the elevation of the ramp leading to the front door does not
comply with ADA code. That will have to be addressed.
Storage Vaults:
There are two scheduled for the new building. It was learned that neither
were sufficient to meet the fire code ratings required in Massachusetts.
Ooops, that matter is now being addressed. One needs vaults to preserve the
town’s history, and to meet statutory requirements. While it may be ok with
some, or even welcomed, the fire ratings are there for good reason.
The Driveway Pond:
Who can forget the large pool of water
that never seemed to go away. An engineering/architectural blunder of the
first degree. Who ended up paying for that one? We did. The work was re-done
by our own Highway Department. Superintendent Paul Basler tells us "It will
work." We believe him, but why were others not held responsible?
Clerk of the Works:
Aside from a Building Committee, few realize that there is a Clerk of
the Works for the project. That individual would be Jim Colman, who also
serves as Assistant Building Inspector. Would you believe the rate of pay
for the project is $1,000 a week? Not bad. Now we love Jim Colman, but
perhaps, for that kind of money, we could have been a bit more vigilant? And
these items are just those we learned. There must have been more to cause
several months of delays.
Sewer Functionality:
Brian Donahoe tells us that the Sewer Commissioners cannot guarantee the
functionality of the Town Hall system. He said that no matter how often his
Commission has requested it, he has yet to receive professional plans of the
sewer connection. The company that did the connection was Crystal
Construction, owned by Board of Health member Joe Casna. Casna had one of
his employees do the connection, Selectman Richard Cretinon. Donahoe said
that his Commission will no longer accept applications of any kind from
either individual "since we no longer consider them separate." He said that
Cretinon was signing paperwork on behalf of Casna. When the practice was
questioned, Casna provided the Commissioners with a document authorizing
Cretinon to sign for him. We question what type of work Casna may be
applying for since his Health Board seat would preclude most involvement due
to conflict of interest. Cretinon, as a Selectman cannot attain Special
Employee status which would allow him to gain financially by doing work for
the town he oversees as the highest elected public official.
Grinder vs. Gravity:
Had the Town Hall been mounded a mere 12 inches higher, a gravity fed system
would have been not only possible, but more practical and cost effective.
Grinder pumps require maintenance, electrical costs and are prone to
failure. A lousy call here!
One-Stop Service?
We think not. Wasn’t one of the reasons to build a state-of-the-art complex
to put government under one roof in order to address the needs of the
public? One would think, but old habits die hard. The Sewer Commissioners
have informed the Town Administrator that they will be remaining behind at
the pumping station. Although space has been provided for them, they will
not be moving. Neither will the Water Department. In this instance, space
was never provided. We fully realize that once you occupy your own little
piece of the world, you hate to join the general population. The reasons are
predictable; all our records and personnel are here. Well, move them, like
everybody else. In truth, it’s really about hunkering in, remaining more
isolated, and more in control. We have heard there is a move afoot to
require them to move, via an article at a Town Meeting. It’s a shame that it
must be accomplished with kicking and screaming. The issue is convenience,
for the public. By the way, is the Elm Street Pumping Station fully
handicapped accessible? |